Eiffage Génie Civil has just won the design and build contract for a primary clarification facility on the Seine Aval water treatment plant site (78).
The operation will cost 387 M€ overall, including 212 M€ for the structural engineering work. The contract was won in consortium with leader OTV.
The service order will be delivered in April by the Siaap (Paris region public sanitation service). The project deadline is 66 months, including a 19-month design period (until 2018) and a 35-month works phase to be launched in early 2019.
Eiffage Genie Civil has already completed several structures linked to the plant's modernization programme launched in the early 2000s. The most recent to date, known as Biosav, was commissioned on 21 February 2017.
-
27.06.2025Inauguration of the first ground-mounted solar power...As part of its low-carbon strategy, the APRR motorway network has entrusted teams from TotalEnergies with the construction and operation of a 5 MWp photovoltaic... -
03.06.2025Eco Skills Challenge 2025: Meet the WinnersThe grand finale of the 4th edition of the Eco Skills Challenge took place on Tuesday, May 27, at the Maison de l’Océan. Congratulations to the winners, as well... -
13.05.2025Financial information at 31 March 2025Revenue of €5.6 billion, up 8.3% (up 19.1% in Europe excluding France)