Here is an update on our progress:
- Earthworks are complete.
- Dry and wet utilities are nearly finalized.
- The tracks have been laid.
- Structural work on the buildings is finished, and secondary work packages are now underway.
- The underfloor wheel lathe is installed.
- Signaling activities have commenced.
- The overhead crane and lifting table are currently being installed.
- Catenary system installation is ongoing.
This achievement brings us one step closer to the inauguration of the largest SNCF Group maintenance center in France, which will be dedicated to servicing the RER D and Line R trainsets.
The consortium, led by Eiffage Génie Civil, is leveraging a wide range of expertise from across the Eiffage group, including Demcy, Eiffage Rail, Eiffage Énergie Systèmes, Eiffage Route, SAVARE, and Ferlioz from Eiffage Concessions.
to discover also
-
22.07.2026In the heart of the Mont-Blanc massif, Ævia applies...In the municipality of Megève, Ævia has successfully renovated the Cassioz bridge. -
21.07.2026Two new tunnel boring machines for Line 15 EastThis Friday, July 17, 2026, Eiffage Génie Civil, together with the project owner Société des grands projets, has officially accepted two new tunnel boring machines... -
17.07.2026The 37th edition of the Baticup was marked by another...Two Eiffage Génie Civil crews were involved in this frigate which took place in Quiberon Bay departing from the port of La Trinité-sur-Mer (56).