In figures, this project represents :
5 months of work
6,100 m of drilling
1,700 m² of nailed wall
500 m³ of shotcrete
19 m high wall
Congratulations to our mobilised teams!
Thank you to Spie batignolles for their confidence!
Discover the images of these projects on video.
-
24.11.2023Eiffage Génie Civil wins contract for new section of...Eiffage Génie Civil has won the contract to build the new section of the E18-E39 motorway in Kristiansand, Norway, worth more than €234 million.
-
17.11.2023Eiffage just signed with EDF a contract for civil engineering...Eiffage, through its subsidiary Eiffage Génie Civil, just signed the contract with EDF to carry out the main civil engineering works for the first pair of EPR2-type...
-
30.10.2023In the Pyrenees, Ævia refurbished the Izourt damÆvia refurbishes the Izourt dam in the PyreneesAt an altitude of 1,645 m, our Aevia teams were involved in refurbishing the waterproofing of the Izourt dam, located...