While the overall operation lasted a month, the most critical phase took place during the weekend of April 17th and 18th. The objective was to clear this strategic route and reopen the lanes as quickly as possible, while ensuring complete safety.
The project in numbers:
- 50 people mobilized on-site
- 20 heavy machines operating simultaneously
- 20 hours of non-stop work
True to our eco-responsible commitments, the materials from the old bridge were transported to a dedicated platform to be screened and crushed. They will soon be given a second life!
Congratulations to the teams for this collective achievement and their perfect synergy on the ground
Watch the deconstruction in video.
to discover also
-
07.07.2026Eiffage Génie Civil installs two mooring dolphins in...As part of the reconstruction of berthing piles No. 1 and No. 2 for the oil jetty, our Eiffage Génie Civil teams successfully completed this major project in just... -
07.07.2026Toulouse metro: finishing works begin at Colomiers...A new milestone has been reached. -
03.07.2026First commissioning on the E18 motorway in Norway!This Friday, July 3, our Eiffage Génie Civil teams commissioned a first section of the E18 motorway, which notably includes the Grenland cable-stayed bridge. A major...