As part of the reconstruction of berthing piles No. 1 and No. 2 for the oil jetty, our Eiffage Génie Civil teams successfully completed this major project in just two months.
This complex project, conducted from a barge, required state-of-the-art expertise in a challenging maritime environment to carry out the key operations:
- Removal of existing structures
- Vibro-driving and piling of steel piles nearly 1.6 meters in diameter
- Installation of mooring structures and equipment (fenders and bollards)
To achieve this, we mobilized substantial maritime and land-based resources, including our EGCM01 barge, a 300-ton crane, and an IQIP S90 pile-driving hammer.
This operation enhances the safety of mooring operations and the overall performance of the port's oil infrastructure, a critical component of Togo's maritime economy.
Mooring dolphins are piles anchored to the seabed, designed to withstand the significant forces exerted by vessels and maritime conditions.
Client: Port Autonome de Lomé (Port Authority of Lomé)
Project Manager: INROS LACKNER SE
Execution Studies: Eiffage Génie Civil
Credit: Eiffage
-
18.11.2026Toulouse Metro: Our TBM Jeanne Marvig has just achieved...Jeanne Marvig has just completed its third breakthrough at the future Saint-Martin - Airbus station. -
17.11.2026In Benin, Eiffage Génie Civil has completed and handed...At the Autonomous Port of Cotonou (PAC), our Eiffage Génie Civil teams have completed and handed over two new phases of work for the basin expansion and the renovation... -
02.11.2026Toulouse Metro: TBM Berthe de Puybusque reaches a new...Following the Fondeyre and Ponts-Jumeaux stations, the Tunnel Boring Machine (TBM) Berthe de Puybusque has successfully completed its third breakthrough, reaching...