31.08.2023
In Colombia, Eiffage Génie Civil Marine drives the first offshore pile on the Puerto Antioquia project
In Colombia, on the Puerto Antioquia project, our teams from Cotema - a consortium comprising Eiffage Génie Civil Marine (lead contractor) and Termotecnica - installed the first offshore pile from the EGCM04 barge!
![In Colombia, Eiffage Génie Civil Marine drives the first offshore pile on the Puerto Antioquia project](/files/live/sites/eiffagev2/files/Actualites/whatsapp-image-2023-08-30-at-14.53_2_1.png)
This major milestone marks the start of offshore activities, which include :
- the installation of more than 1,000 piles with a diameter of 1,524 mm and an average length of 75 m,
- the installation of prefabricated elements weighing more than 70 t,
- and the concreting of more than 80,000 m³ of concrete from the plant installed on the EGCM03 barge.
For these large-scale operations, 15 ships and barges will be mobilised over the next 15 months, including the barges EGCM03 and EGCM04.
The piles will be manufactured entirely on site from steel coils. To date, the plant has already produced the equivalent of 25 piles.
Congratulations to the Cotema teams for achieving this important milestone in complete safety!
-
04.07.2024Discover the behind-the-scenes video of the refurbishment...The Jeanne-Marvig tunnel boring machine arrived at the Toulouse Metro Line C construction site at the end of June. Discover the behind-the-scenes of its refurbishment...
-
01.07.2024In Toulouse, Eiffage Génie Civil inaugurates the Robert...Our teams participated in the inauguration of the Robert Poujade footbridge, formerly Rapas, on June 22, 2024, in the presence of Jean-Luc Moudenc, Mayor of Toulouse...
-
27.06.2024The Cutterhead of the Tunnel Boring Machine Jeanne...At the end of June, on the Toulouse Metro Line C construction site, the tunnel boring machine Jeanne Marvig was unveiled at the Colomiers Gare shaft site. The event...