08.11.2019
Grand Paris Express: the cutting wheel of the 2nd TB2 TBM downed
And two! After Camille's in Créteil, it was on the site of the future Bry-Villiers-Champigny station that the cutting wheel of the second tunneling machine of lot T2B of line 15 South of the Grand Paris Express was lowered to the bottom of the shaft.
On site, the assembly of the machine continues, while the civil engineering teams have finished the station floor, leaving all the space for the installation of the necessary installations for its start-up.
The beginning of the excavation, 3 kilometres long until the 1001P Salengro roadwork in Champigny, will take place at the very beginning of 2020.
Photos Credit: Hervé Piraud
-
25.04.2024Eiffage Civil Engineering has excavated the first 3...The first 3 kilometers of tunnel for Lot 2 have been excavated as part of the construction of the future VL8 collector! The tunnel boring machine, named Béatrice,...
-
24.04.2024
-
19.04.2024The Foundations teams at Eiffage Civil Engineering...For this expansion project, carried out for the Luberon Shopping Center, the works include: