Controlled deconstruction in a constrained environment, in Nanterre (92), by Demcy
Our Demcy teams successfully completed the stripping, asbestos removal, deconstruction, and backfilling of the 37-meter-high Primevères tower, using specific technical resources and a methodology dictated by the site's environment.
The operation required the manual demolition of a 42-meter chimney, the removal of the elevator machinery, and the dismantling of the tower using a 974 high-reach excavator under dust suppression mist.
Heavy-duty protection was installed around a live electrical transformer that supplied the neighborhood, in addition to the placement of peripheral concrete blocks.
The removal of 5,000 tons of concrete was concentrated in August, during the summer holidays, to preserve the tranquility of the neighboring school.
Congratulations to all the teams on the ground for their high standards and expertise!
An operation carried out on behalf of Adoma CDC Habitat (Client) and CoBe Architecture et Paysage (Project Manager), in partnership with Désamiantage France Démolition (DFD) and A.D.T.L.
Credit: Atypix
-
28.09.2026Lourdes: Pope Leo XIV unveils a sculpture on the bridge...During a visit to the city of Lourdes, a major Catholic pilgrimage site, the Sovereign Pontiff, alongside Thierry Lavit, Mayor of Lourdes, unveiled this work by... -
24.09.2026Toulouse Metro: Completion of civil engineering works...A major milestone has been reached on Lot 2 of the Toulouse Metro's Line C, with the handover of the Daturas Workshop-Garage gallery site by the Eiffage Génie Civil... -
14.09.2026Neomat CAM plant: consortium in charge of civil engineering...Neomat CAM, a joint venture between XTC New Energy and Orano, has awarded to the consortium led by Eiffage the contract for earthworks and construction of the buildings...