27.08.2024
Update on the CDG Express
In Saint-Denis, on the Charles-de-Gaulle Express construction site, zone D, Eiffage Génie Civil installed three mixed concrete/metal decks this summer.
- OA13-14: 60 m, 650-ton side-beam railway bridge (RAPL)
- OA15: 18 m, 250-ton embedded beam deck (TPE)
- OA16: 60 m, 750-ton side-beam railway bridge (RAPL)
The operation took place from July 15 to August 14, 2024, during a temporary traffic interruption (ITC).
1,700 m³ of fill was required to create the sliding paths over the three existing SNCF tracks. The three decks, which had previously been assembled in a prefabrication area, were then transferred to their final location using self-propelled modular transporters, known as Kamags. The temporary stabilization and jacking of the decks were carried out in synergy with Ævia teams. The civil engineering work, which began in September 2022, is expected to be completed by the end of 2024.
In total, 9,000 hours of workforce integration will have been completed on this site. Congratulations to all the teams who rose to the challenge during the Paris Games!
SNCF Réseau
Consortium: Eiffage Génie Civil - NGE GENIE CIVIL - Eiffage Métal
Subcontractors: Ævia - CAPOCCI - Sarens
-
28.09.2026Lourdes: Pope Leo XIV unveils a sculpture on the bridge...During a visit to the city of Lourdes, a major Catholic pilgrimage site, the Sovereign Pontiff, alongside Thierry Lavit, Mayor of Lourdes, unveiled this work by... -
24.09.2026Toulouse Metro: Completion of civil engineering works...A major milestone has been reached on Lot 2 of the Toulouse Metro's Line C, with the handover of the Daturas Workshop-Garage gallery site by the Eiffage Génie Civil... -
14.09.2026Neomat CAM plant: consortium in charge of civil engineering...Neomat CAM, a joint venture between XTC New Energy and Orano, has awarded to the consortium led by Eiffage the contract for earthworks and construction of the buildings...