On the HS2 project, successful launching by Eiffage Métal teams
In the United Kingdom, Eiffage Métal teams have successfully carried out the largest launching on the HS2 high-speed rail project!
Four days were required to position the steel deck of the Small Dean viaduct over the A413—a highly frequented route—and the railway line connecting London’s Marylebone district to the town of Aylesbury.
The 350-meter-long, 4,500-ton deck was moved using Teflon pads, a 20-ton winch, and a 450-ton cable jack.
This key milestone in the project is the result of meticulous and rigorous preparation, carried out with determination by Eiffage Métal’s specialized teams.
For David Feghali, Project Director, “The innovative solutions and technical challenges successfully met during this operation reinforce Eiffage Métal’s position as a key player in complex projects.”
Congratulations to the teams for achieving this important milestone!
-
04.06.2026Eiffage wins as part of a consortium the contract to...Eiffage, through its German subsidiaries Eiffage Infra-Bau and SEH, has won in a consortium with Mostostal Kraków, the contract from the city of Nuremberg in Germany,... -
28.05.2026Eiffage and Arabelle Solutions sign a partnership agreement...Eiffage, through its subsidiary Eiffage Métal, and Arabelle Solutions, a subsidiary of EDF, signed a 12-year partnership agreement for the manufacturing of modules... -
21.01.2026Eiffage wins in consortium the contract to replace...Eiffage, through SEH Engineering– a German subsidiary of Eiffage Métal – has secured the contract to build the new Levensau Bridge on the Kiel Canal in northern...