20.07.2022
Great Turtle Ahmeyim project : central hub completed
After successfully completing the installation of the 21 caissons, our Eiffage Génie Civil Marine teams have just finished the central platform of the hub located 10 km from the coast on the Mauritania-Senegal border.
This platform represents more than 3 200 tonnes of steel structure and 200 prefabricated concrete elements installed by two 300-tonne cranes moving forward.
All these elements were supplied by cargo barges from our marine base in the port of Dakar. A fleet of fifteen vessels was operated by Eiffage Génie Civil Marine teams, including a 300-bed floatel.
Close management of simultaneous operations with our partner Saipem ensured safety and adherence to the schedule.
In line with our commitment to employment, more than 75% of our teams on this operation were made up of local personnel, the majority of whom were experiencing offshore work for the first time.
Both at sea and on land, our employees showed great professionalism, well done !
-
02.11.2026Toulouse Metro: TBM Berthe de Puybusque reaches a new...Following the Fondeyre and Ponts-Jumeaux stations, the Tunnel Boring Machine (TBM) Berthe de Puybusque has successfully completed its third breakthrough, reaching... -
21.10.2026TELT Lyon-Turin: Eiffage Génie Civil inaugurates phase...On Monday, October 19th, our Eiffage Génie Civil teams inaugurated the phase 2 railway interconnection infrastructure in Saint-Jean-de-Maurienne—a key milestone... -
16.10.2026Eiffage Génie Civil has completed the installation...Objective: To produce 1 million cubic meters of concrete for the EPR2 project in Penly.