15.10.2024
In Côte d'Ivoire, the final adjustments to the Singrobo-Ahouaty dam by Eiffage Civil Engineering
A look back in pictures at the final adjustments to the Singrobo-Ahouaty hydroelectric dam in Côte d'Ivoire, a 1,400-meter-long structure with a reservoir capacity of 110 million m³.
Completed installations:
- The tailrace and drainage canal
- The water intakes
- The spillway, consisting of 3 gates, each 11 meters wide, with a total capacity of 2,745 m³ per second
- The transformer substation and 90,000 V power line
Ongoing installations: The assembly of the 22 MW horizontal-axis Kaplan turbines is currently underway.
This dam is designed to deliver 44 MW of power to the Ivorian interconnected grid, thereby strengthening Côte d'Ivoire's decarbonized electricity production capacity.
A design-build project with RMT for Ivoire Hydro Energy.
to discover also
-
09.06.2026Toulouse metro: tunnel boring machine Lise Enjalbert...Our tunnel boring machine, Lise Enjalbert, and its team have achieved a crucial milestone with the second breakthrough at the future Blagnac station. -
03.06.2026Three new service quays completed in Grand-Lahou, Côte...Our Eiffage Génie Civil Marine teams have finalized the construction of three new service quays, each measuring 20m x 12m. -
29.05.2026Toulouse metro: TBM Jeanne Marvig completes its second...The Jeanne Marvig tunnel boring machine (TBM) has successfully completed its second breakthrough, breaking through the diaphragm wall of the future Fontaine Lumineuse...