From June to October, Eiffage Rail will be carrying out the annual overhaul of the tracks on the Orlyval metro between Antony and Orly airport during night work,
From 3 to 14 July, on the T1 tramway, teams will renew the tracks - nearly 350 metres of rail at the crossroads - and the road surface at the Hôtel-de-Ville station in Bobigny,
Finally, during the summer, following on from the work carried out at Saint-Rémy-lès-Chevreuse station on the RER B in 2019 - laying 10 switches and replacing 900 metres of track - Eiffage Rail's teams will continue to renew tracks 4 and 5 at the station - i.e. 450 metres of track - to optimise train reversal manoeuvres.
In total, about fifty journeymen will be mobilized on these 3 summer workcamps.
Photo credit: Eiffage Rail
-
30.04.2024A feminine head for Harwig, a subsidiary of Eiffage...Since 2022, Maureen Nederhoed has been the general manager of Harwig, a subsidiary of Eiffage Energie Systèmes in the Netherlands. She perpetuates the family saga...
-
30.04.2024Environment: Eiffage Strengthens Its Biodiversity Charter...Having already made commitments to sustainable development, biodiversity, water and aquatic environments, low carbon, and circular economy, the Eiffage Group is...
-
17.04.2024Caïus 2024: Eiffage wins two awardsDaniel Buren's artwork "Like colors fallen from the sky, in situ and in motion," temporarily exhibited at the Liège train station in Belgium and supported by Eiffage,...