- 2,000 meters of drilling
- 61 tons of reinforcements
- 900 m² of nailed walls
- 180 m³ of concrete
- 30 m³ of grout produced
This project is part of the dynamic development and modernization of commercial infrastructure in the region, contributing to the economic vitality of Pertuis and Luberon.
Project Management: MARRAUD ARCHITECTURE & ENGINEERING
View images of this project!
Credit: Sly Productions
-
25.04.2024Eiffage Civil Engineering has excavated the first 3...The first 3 kilometers of tunnel for Lot 2 have been excavated as part of the construction of the future VL8 collector! The tunnel boring machine, named Béatrice,...
-
24.04.2024
-
17.04.2024On the CEA Valduc site project, where Eiffage Civil...The agenda for this training day in hazardous environments included two scenarios aimed at achieving three objectives crucial for the successful completion of this...